Hi,
After the cycle for Geany 0.20 is going to end soon, we need to think about scheduling a new release of Geanys combined plugins project which are depending on Geany 0.20.
Given that the plugins shouldn't be release too far away from Geany core, but there is still some work to do in terms of e.g. removing some ugly compiler warnings I do suggest these schedule:
Last changes which are touching strings: Saturday, 18th String freeze: 19.12 Last translations checkin: 27.12 Release: ~ 28.12
This would give us about 1 week for some translating work and all in all >2 weeks for fixing last outstanding bugs and issues.
Of course the times are depending on the status of developers after the Xmas holidays :)
What do you think? Is this something doable? ;)
Cheers, Frank