On 01/04/14 00:49, Lex Trotman wrote:
Since we are about to produce a new release I propose a change to the Geany workflow.
More regular releases.
Acknowledging that Geany hasn't the number of contributors that say firefox has, monthly would seem too often, so instead I propose an 8 week schedule:
- week 4 feature freeze, alpha release for testing
- week 6 string freeze, beta release for testing
- week 7 release candidate
- week 8 THE RELEASE!!!
Then we don't need to be so careful about changes, because problems only last for a couple of months until the next release, and since only a few new features will be added each release nobody will feel that they have lost much if they have to downgrade due to bugs.
I therefore propose that the eight week period should start today April 1.
Yeah, very great idea. And of course we must do the same for Geany-Plugins!
Muhahaha, well done Lex. Nice one :).
Regards, Enrico